Foundation works are underway at Bramfelder Dorfplatz station in Hamburg, part of the ongoing urban transport infrastructure development. The project involves the execution of deep diaphragm walls to support excavation activities and ensure ground stability in a densely built urban environment.

On this site, ICOP operates a Casagrande KHD28 hydraulic diaphragm wall grab mounted on a B300XP-2 base machine. The configuration is designed for the excavation of large rectangular panels, enabling controlled trenching operations for diaphragm wall construction.

🔧 Technical data:
• Panel size: 1500 × 3200 mm
• Maximum depth: 50 m
• Hydraulic grab: KHD28

Thanks to ICOP for choosing our equipment for this project.